PHASE I PROJECTS
Burgangchhu HPP
Location : Nangkhor, Zhemgang
Capacity : 54 MW
Project scheme : Run-of-the-river
Design energy : 260.51 MU
Project cost : Nu. 3,565.25 million
Project schedule : 2022 – 2025
Yungichhu HPP
Location : Medtsho, Lhuentse
Capacity : 32 MW
Project scheme : Run-of-the-river
Design energy : 157.6 MU
Project cost : Nu. 3,660 million
Project schedule : 2022 – 2025
Suchhu HPP
Location : Sangbaykha, Haa
Capacity : 18 MW
Project scheme : Run-of-the-river
Design energy : 76.57 MU
Project cost : Nu. 2,095 million
Project schedule : 2022 – 2024
PHASE II PROJECTS
Jomori HPP
Location : Jomotshangkha, SJ
Capacity : 90 MW
Project scheme : Run-of-the-river
Design energy : 367 MU
Project cost : Nu. 8,509 million
Project schedule : 2023 – 2028
Druk Bindu I&II HPP
Location : Tendu, Samtse
Capacity : 26 MW
Project scheme : Run-of-the-river
Design energy : 109.82 MU
Project cost : Nu. 2,654.49 million
Project schedule : 2023 – 2026
Gamri I HPP
Location : Sakteng, Trashigang
Capacity : 54 MW
Project scheme : Run-of-the-river
Design energy : 228 MU
Project cost : Nu. 5,876.42 million
Project schedule : 2023 – 2027
Begana Integrated HPP
Location : Begana, Thimphu
Capacity : 25 MW
Project scheme : Run-of-the-river
Design energy : 104 MU
Project cost : Nu. 2,694.48 million
Project schedule : 2023 – 2026